How-To: Create Annual Plan

Prerequisites​

  • You must have the CAE or Manager role
  • Audit Universe should be populated with entities and risk assessments

Step 1 — Navigate to Planning​

Click Planning in the left sidebar.

Planning list view

Step 2 — Click "New Annual Plan"​

Click the + New Annual Plan button.

Step 3 — Set Plan Details​

FieldRequiredDescription
Plan Year✅The fiscal year (e.g., 2027)
Title✅Plan name (e.g., "FY2027 Internal Audit Plan")
DescriptionRecommendedOverview of the plan's objectives and scope
OwnerAutoDefaults to current user (CAE)

Step 4 — Add Plan Items​

Each plan item represents a planned audit engagement. Click + Add Item for each:

FieldRequiredDescription
Title✅Engagement name
Universe Item✅Link to Audit Universe entity
Type✅Compliance, Operational, Financial, IT, Special
PriorityAutoCalculated from universe risk score
Planned Quarter✅Q1, Q2, Q3, or Q4
Estimated HoursRecommendedBudgeted hours for this engagement
Lead AuditorRecommendedPrimary assigned auditor

AI-Assisted Item Generation​

Click AI Generate Plan Items to have the AI suggest plan items based on:

  • Universe items with the highest risk scores
  • Entities not audited in the last 12+ months
  • Previous findings requiring follow-up
  • Regulatory requirements mandating periodic review

Review each suggestion and accept or reject individually.

Step 5 — Allocate Resources​

Navigate to the Resources tab within the plan:

  1. View the Resource Calendar showing auditor availability
  2. Drag-assign auditors to plan items
  3. Monitor Capacity Utilization bars to prevent overcommitment
  4. Adjust planned quarters if resources are constrained
Expected Result

The capacity utilization bar turns amber (>80%) or red (>100%) when an auditor is overallocated. Resolve overallocation before submitting for approval.

Step 6 — Submit for Approval​

When the plan is complete:

  1. Click Submit for Review
  2. The plan moves to "Under Review" status
  3. The CAE receives a notification to approve
  4. CAE reviews the plan, risk analysis, and resource allocation
  5. CAE approves → plan moves to "Approved" status

Step 7 — Execute the Plan​

Once approved:

  • Plan items can be converted to Engagements by clicking Create Engagement on each item
  • Progress is tracked automatically as engagements move through their lifecycle
  • The planning dashboard shows real-time completion percentage

Mid-Year Plan Revisions​

Plans can be revised during the year:

  1. Click Revise Plan on an approved plan
  2. A new version is created (previous version is preserved)
  3. Make changes to items, resources, or timeline
  4. Re-submit for CAE approval
  5. Version comparison shows exactly what changed

Best Practices​

  1. Start with risk data — populate the Audit Universe before planning
  2. Use AI suggestions — AI identifies coverage gaps you might miss
  3. Check capacity before approving — ensure no auditor exceeds 100% utilization
  4. Build in buffer — plan for 80% capacity to accommodate ad-hoc requests
  5. Review quarterly — reassess plan items based on emerging risks
  6. Document rationale — record why certain items were prioritized or deferred